WELCOME TO POWER ENGINEERS

"Don't Do Different Things - Do Things Differently"



May 14, 2011

EMISSION STANDARDS - POWER PLANTS

The emission standards for thermal power plants in India are being enforced based on Environment (Protection) Act, 1986 of Government of India and it’s amendments from time to time.A summary of emission norms for coal and gas based thermal power plants is given below in Tables
Environmental standards for coal & gas based power plants
Capacity
Pollutant
Emission limit
Coal based thermal plants
Below 210 MW
Particulate matter(PM)
350 mg/Nm3
210 MW & above

150 mg/Nm3
500 MW & above

50 mg/Nm3
Gas based thermal plants
400 MW & above
NOX(V/V at 15% excess oxygen)
50 PPM for natural gas;
100 PPM for naphtha
Below 400 MW & up to 100 MW

75 PPM for natural gas;
100 PPM for naphtha
Below 100 MW

100 PPM -naphtha/natural gas



The norm for 500 MW and above coal based power plant being practiced is 40 to 50 mg/Nm and space is provided in the plant layout for super thermal power stations for installation of flue gas desulphurisation (FGD) system. But FGD is not installed, as it is not required for low sulphur Indian coals while considering SO X emission from individual chimney
 Stack height requirement for SO2 control
Power Generation Capacity
Stock Height (Metre)
Less than 200/210 MWe
H = 14 (Q)0.3 where Q is emission rate of SO 2 in kg/hr, H = Stack height in meters
200/210 MWe or
less than 500 MWe
200
500 MWe and above 275 (+ Space provision for FGD systems in future)
However the norms for SOx are even stricter for selection of sites for World Bank funded projects. For example, if SOx level is higher than 100 ? g/m 3, no project with further SOx emission can be set up; if SO X level is 100 ? g/m 3, it is called polluted area and maximum emission from a project should not exceed 100 t/day; and if SOx is less than 50 ? g/m 3, it is called unpolluted area, but the SOx emission from a project should not exceed 500 t/day. The stipulation for NOX emission is that its emission should not exceed 260 gram s of NOX per Giga Joule of heat input.
In view of the above, it may be seen that improved environment norms are linked to financing and are being enforced by international financial institutions and not by the policies/laws of land.

May 12, 2011

BOILER WATER TREATMENT,SCALES & CORROSION

In general there are two types of boilers, low pressure and high pressure:
 A) Low pressure boilers will be found heating water or steam to be circulated around a building for heating purposes via radiators. These systems are "closed circuit" types and require little or no "make" water to top them up. Mostly low pressure boilers operate below 10 psi.
B) High pressure boilers will be found in industry, generating steam for a variety of uses, locomotion via a steam engine, or for end use of steam in laundries, rubber product manufacturing, wood pulp products, food manufacture etc. These boilers operate at over 10 psi and all require constant "make up" water as some of the steam is used.
Boiler feed water ("BFW") may either be the same as the makeup water, or may consist of returned steam condensate, or (as in most cases) will be a mixture of both.
The relative amounts of makeup and condensate may vary. A typical figure is 5% makeup with 95% condensate, but this depends on how the steam plant is operated and how much of the steam is condensed and recovered for recirculation.
In order to be non-scaling, the BFW must be a softened or demineralised water . In order to be non-corrosive to the carbon-steel or low-alloy steel components from which boilers are usually constructed, the water must be thoroughly deaerated. This is partially achieved by thermomechanical means (use of deaeration heating tanks), while the last traces of dissolved oxygen are removed by chemical agents ("oxygen scavengers").

Oxygen scavengers include both volatile products (e.g., hydrazine, or other organic products like carbohydrazine, hydroquinone, diethylhydroxyethanol, methylethylketoxime, etc.) and non-volatile salts (normally: sodium sulphite, Na2SO3, or a derivative thereof). The latter salts often contain catalysing compounds to increase of rate of reaction with dissolved oxygen (e.g., cobaltous chloride).
Oxygen Scavengers:
While the oxygen scavenging salts tend to react rapidly with oxygen, even at lower temperatures, their reaction products result in increased levels of total dissolved solids in the boiler feedwater.
To minimize this disadvantage, the salt should be fed to the storage tank of the deaerating heater and care should be taken that no precipitates are introduced into the boiler feed.
As rule of thumb, one typically feeds 10 parts of sodium sulphite per part of oxygen (to compensate for reaction with atmospheric oxygen and for impurities in the sodium sulphate).
Volatile oxygen scavengers are normally employed for higher pressure systems (e.g., above 1000 psig). These materials may react directly with oxygen and or directly with carbon steel boiler surfaces to form gamma iron oxide or magnetite. The formation of such "oxygen-impervious" oxide films precludes excessive corrosion.
Except for the common hydrazine (N2H4), most other volatile organic oxygen scavengers are sold under some proprietary name. The use of hydrazine in boiler feedwater is very common and very well documented. Because hydrazine typically does not react with oxygen at a rapid rate at lower temperatures, it may not be the preferred oxygen scavenger for low temperature boiler feedwater systems. In addition, hydrazine is seriously toxic and great care should be taken in its handling. Food production sites should consider seriously the potential consequences of using highly poisonous chemicals.
Scaling:
As water is heated and converted into steam, contaminants brought into a boiler with makeup water are left behind. The boiler functions as a distillation unit, taking pure water out as steam, and leaving behind concentrated minerals and other contaminants in the boiler. Scale forms as a result of the precipitation of normally soluble solids that become insoluble as temperature increases. Some examples of boiler scale are calcium carbonate, calcium sulphate, and calcium silicate.
Corrosion
Corrosion is a general term that indicates the conversion of a metal into a soluble compound. 
In the case of boiler metal, corrosion is the conversion of steel into rust. In a boiler, two types of corrosion are prevalent:
1.)     Oxygen pitting corrosion, seen on the tubes and in the preboiler section.
2.)      Low pH corrosion, seen in the condensate return system.
Corrosion of either type can lead to failure of critical parts of the boiler system, deposition of corrosion products in critical heat exchange areas, and overall efficiency loss.
Carryover:
Carryover is caused by either priming or foaming. Priming is the sudden violent eruption of boiler water, which is carried along with steam out of the boiler, usually caused by mechanical conditions. Priming can cause deposits in and around the main steam header valve in a short period of time. Foaming causes carryover by forming a stable froth on the boiler water, which is then carried out with the steam. Over a period of time, deposits due to foaming can completely plug a steam or condensate line.
Typical Boiler Failures and Causes:
Oxygen Pitting:
The time when a boiler system is most vulnerable to oxygen pitting is during idle periods. In order to prevent oxygen pitting during these times it is important to utilize proper storage techniques. Please see our technical tip on this subject at Dry Storage of Boilers and Wet Storage of Boilers.
 When a boiler is in operation, oxygen pitting is most likely to occur in feedwater heaters or economizer tubes, since this is this is where the water is first heated above the deaerator temperature. Maintaining a properly operating deaerator with sufficient oxygen scavenger is the best method of prevention.
 If oxygen pitting is noticed, it is important to note if it is “old” or active pitting. Active oxygen pits can be distinguished by the red-brown tubercle which, when removed, exposes black iron oxide within the pit.
Short-Term Overheating: 
This type of failure is usually indicated by a "thin-lipped" burst of the boiler tube. These failures occur when water circulation in the tube is interrupted, and the flue gas temperatures cause a rapid overheating of the metal to a point where the metal becomes highly plastic and a violent burst occurs. Typical causes of short-term overheating are circulation problems caused by poor operation (sudden increase in steam demand or low water level) or design, and tube blockage. Tube blockage normally occurs from deposition in the tube or supply header.
Long-Term Overheating:
 This type of failure is usually indicated by a "thick-lipped" burst of the boiler tube. Long-term overheating can result from excessive deposition, flame impingement, mild flow restrictions, or poor water or flue gas circulation patterns. Probably the most common of these is excessive deposition, which prevents proper heat transfer and excessive metal temperatures. This prolonged overheating of the tube causes metal degradation to the point that in can no longer handle the operating pressure and a "thick-lipped" failure occurs. 
Caustic Gouging:
 Caustic gouging occurs when NaOH concentrates under porous boiler water deposits. An example of such deposition would be iron, which tends to be porous. Essentially, what occurs is that boiler water is present in the deposit. As steam escapes, the NaOH concentration increases dramatically, dissolving the protective magnetite and boiler tube metal.
 In addition to the gouging of the boiler tubes you may also notice a white substance (sodium carbonate) outlining the edges of the original deposit.
 There are other failure mechanisms such as caustic and hydrogen embrittlement, stress corrosion cracking and steam blanketing. In this tip we have dealt with those we feel are the most prevalent. If you believe that you have a failure that does not fit into one of the categories we discussed please feel free to contact our staff. Finally, for a complete analysis and understanding of a failure, a sample should be sent to an independent metallurgical lab.

 



May 10, 2011

RANKINE CYCLE -PRINCIPLE

A Rankine cycle describes a model of steam-operated heat engine most commonly found in power generation plants. Common heat sources for power plants using the Rankine cycle are the combustion of coal, natural gas and oil, and nuclear fission.
The Rankine cycle is sometimes referred to as a practical Carnot cycle because, when an efficient turbine is used, the TS diagram begins to resemble the Carnot cycle. The main difference is that heat addition (in the boiler) and rejection (in the condenser) are isobaric in the Rankine cycle and isothermal in the theoretical Carnot cycle. A pump is used to pressurize the working fluid received from the condenser as a liquid instead of as a gas. All of the energy in pumping the working fluid through the complete cycle is lost, as is all of the energy of vaporization of the working fluid, in the boiler. This energy is lost to the cycle in that first, no condensation takes place in the turbine; all of the vaporization energy is rejected from the cycle through the condenser. But pumping the working fluid through the cycle as a liquid requires a very small fraction of the energy needed to transport it as compared to compressing the working fluid as a gas in a compressor (as in the Carnot cycle).
The efficiency of a Rankine cycle is usually limited by the working fluid. Without the pressure reaching super critical levels for the working fluid, the temperature range the cycle can operate over is quite small: turbine entry temperatures are typically 565°C (the creep limit of stainless steel) and condenser temperatures are around 30°C. This gives a theoretical Carnot efficiency of about 63% compared with an actual efficiency of 42% for a modern coal-fired power station. This low turbine entry temperature (compared with a gas turbine) is why the Rankine cycle is often used as a bottoming cycle in combined-cycle gas turbine power stations.
The working fluid in a Rankine cycle follows a closed loop and is reused constantly. The water vapor with entrained droplets often seen billowing from power stations is generated by the cooling systems (not from the closed-loop Rankine power cycle) and represents the waste energy heat (pumping and vaporization) that could not be converted to useful work in the turbine. Note that cooling towers operate using the latent heat of vaporization of the cooling fluid. The white billowing clouds that form in cooling tower operation are the result of water droplets that are entrained in the cooling tower airflow; they are not, as commonly thought, steam. While many substances could be used in the Rankine cycle, water is usually the fluid of choice due to its favorable properties, such as nontoxic and un reactive chemistry, abundance, and low cost, as well as its thermodynamic properties.


There are four processes in the Rankine cycle. These states are identified by numbers (in brown) in the diagram below. 
Process 1-2: The working fluid is pumped from low to high pressure, as the fluid is a liquid at this stage the pump requires little input energy.  
Process 2-3: The high pressure liquid enters a boiler where it is heated at constant pressure by an external heat source to become a dry saturated vapor. The input energy required can be easily calculated using mollier diagram or h-s chart or enthalpy-entropy chart also known as steam tables.   
Process 3-4: The dry saturated vapor expands through a turbine, generating power. This decreases the temperature and pressure of the vapor, and some condensation may occur. The output in this process can be easily calculated using the Enthalpy-entropy chart or the steam tables.  
Process 4-1: The wet vapor then enters a condenser where it is condensed at a constant temperature to become a saturated liquid.



    Apr 30, 2011

    RANKINE CYCLE

    Rankine Cycle:
        Saturated or superheated steam enters the turbine at state 1, where it expands isentropically to the exir pressure at state 2. The steam is then condensed at constant pressure and temperature to a saturated liquid, state3. The heat removed from the steam in the condenser is typically transferred to the cooling water. The saturated liquid then flows through the pump which increase the pressure to the boiler pressure (state 4), where the water is first heated to the saturation temperature, boiled and typically superheated to state 1. Then whole cycle is repeated.


    Oct 1, 2010

    ENVIRONMENTAL REGULATIONS ON TPS

    Thermal power Plants

    Environmental Regulations ON THERMAL POWER STATIONS

    A : Coal Based Thermal Power Plants

    Standards for discharge of liquid effluents



    S.
    No.

    Source

    Pollutants

    Concentration

    (i)

    Condenser
    cooling water
    (once through
    cooling system)

    pH

    6.5-8.5

    Temperature

    More than 10°C than the intake water
    temperature

    Free available
    Chlorine

    0.5 mg/l

    (ii)

    Boiler blow down

    Suspended
    solids

    100 mg/l

    Oil and grease

    20 mg/l

    Copper (total)

    1.0 mg/l

    Iron (total)

    1.0 mg/l

    (iii)

    Cooling tower
    blow down

    Free available
    Chlorine

    0.5 mg/l

    Zinc

    1.0 mg/l

    Chromium

    0.2 mg/l

    Phosphate

    5.0 mg/l

    Other corrosion
    inhibiting
    materials

    Limit to be established on case by case basis

    (iv)

    Ash pond
    effluent

    pH

    6.5-8.5

    SS

    100 mg/l

    Oil & grease

    20 mg/l



    No limits for heavy metals are given at present



    Temperature Limit for discharge of Condenser Cooling Water from Thermal Power plant
    A. New thermal power plants commissioned after June 1, 1999.
    New thermal power plants, which will be using water from rivers/lakes/reservoirs, shall install cooling
    towers irrespective of location and capacity. Thermal power plants which will use sea water for cooling
    purposes, the condition below will apply.
    B. New projects in coastal areas using sea water
    The thermal power plants using sea water should adopt suitable system to reduce water temperature
    at the final discharge point so that the resultant rise in the temperature of receiving water does not






    Rise in temperature of condenser cooling water from inlet to the outlet of condenser shall not be more
    than
    10o C.
    D. Guidelines for discharge point:

    1. The discharge point shall preferably by located at the bottom of the water body at mid-stream
    for proper dispersion of thermal discharge.
    2. In case of discharge of cooling water into sea, proper marine outfall shall be designed to
    achieve the prescribed standards. The point of discharge may be selected in consultation with
    concerned State Authorities/NIO.
    3. No cooling water discharge shall be permitted in estuaries or near ecologically sensitive areas
    such as mangroves, coral reefs/spawning and breeding grounds of aquatic flora and fauna.




    (ii) Emission Standards

    Power generation capacity (MW)

    Particulate matter emission

    Less than 210 MW

    350 mg/Nm3

    210 MW or more

    150 mg/Nm3



    Note:

    Depending upon the requirement of local situations, which may warrant stricter standards as in case of
    protected areas the State Pollution Control Board and other implementing agencies within the
    provisions of the EPA, 1980 may prescribe limit of 150 mg/Nm3 irrespective of the generation capacity
    of the plant.

    Andhra Pradesh Pollution Control Board and Delhi Pollution Control Committees have stipulated
    stringent standards of 115 and 50 mg/Nm3 respectively for control of particulate matter emission.

    (iii) Stack Height Requirement

    In order to proper dispersion of SO2 emissions from thermal power plants, stack height criteria have
    been adopted in the country. However, for larger capacities of boilers (500 m and above), space
    provision for installing FGD system has been recommended;

    Power generation capacity

    Stack height (metre)

    Less than 200/210 MW

    H = 14(Q) 0.3
    where Q is emission rate of SO2 in kg/hr,
    H = Stack height in metre

    200/210 MW or less than 500 MW

    220

    500 MW and above

    275



    Note :

    The power plants sanctioned by CEA earlier to July 1, 1994 may not be required to increase existing
    stack height as per regulation notified, vide Government of India notification no. GSR 742(E) dated
    August 30, 1990 subject to following conditions:

    • The ambient sulphur dioxide and NOx concentrations around the power plant is less than 1/3 th






    prescribed ambient air quality standard for SO2 and Nox for the concerned area.

    • For (1) the power plant shall install adequate number of air quality monitoring stations in and around
    the power stations. The stations should be selected in consultation with the CPCB/SPCB.

    ( Vide office Memorandum No B-34011/1/01/PCI-II dated January 10, 1996 )

    (iv) Use of beneficiated coal

    In order to minimize flyash generation, it was recommended to use beneficiated coal in the power
    plants. The Ministry of Environment & Forests, Govt. of India has promulgated Gazette Notification
    (GSR 560(E) & 378(E), dated September 19, 1997 and June 30, 1998 respectively) on use of
    beneficiated/blended coal containing ash not more than 34 percent w.e.f. June 2002 in the following
    power plants :

    • any thermal power plant located beyond one thousand kilometers from the pit-head and

    • any thermal power plant located in urban area or sensitive area or critically polluted area irrespective
    of their distance from pit-head except any pit-head power plant”.

    The power plants using FBC( CFBC,PFBC & AFBC) and IGCC combustion technologies are exempted
    to use beneficiated coal irrespective of their locations.

    (v) Utilisation of Flyash

    In order to make mondatory use of flyash and flyash based products by the brick kilns, Thermal Power
    Stations and CPWD& State PWDs , vide notification no. S.O. 763(E) dated September 14, 1999,
    Ministry of Environment & Forests has issued directions under sub-rule 3 of rule 5 of EPA, 1986 that

    • No person, located within 50 km radius of any Thermal Power Station, shall to manufacture clay
    bricks, tiles or blocks without mixing atleast 25% flyash or pond ash with soil.

    • Thermal Power Plants shall submit action plan for hundred percent utilization.

    New Plants

    30% within three yrs
    100% within 9 yrs

    Existing Plants

    20% within three yrs
    100% within 15 yrs

    Existing notification on utilisation of flyash was amended vide notification no S.O. 979(E) , dated
    August 27, 2003 .by Ministry of Environment & Forests incorporating

    • No person shall within a radius of 100 kms from thermal power plants, manufacture clay bricks, tiles
    or blocks without mixing atleast 25% of flyash or pond ash with soil.

    • Every construction Agency including private sector builders within a radius of fifty to one hundred
    kilometers from coal or lignite based thermal power plant shall use minimum of following percentage of






    ash based products such as: bricks, block & tiles in their construction work:

    25% by 31 st August, 2004
    50% by 31 st August, 2005
    75% by 31 st August, 2006
    100% by 31 st August, 2007

    In respect of construction of buildings within a radius of fifty kilometers from coal or lignite based
    thermal power plant the following minimum percentage of use of bricks, blocks and tiles shall apply:

    75% by 31 st August, 2004
    100% by 31 st August, 2005

    • Authority sanctioning or renewing mining lease shall not grant or extend the lease if the manufacturer
    does not use the 25% of the Flyash in the manufacturing of bricks, blocks and tiles.

    • Utilisation of Flyash for reclamation of sea subject to compliance of the rules made under the EPA,
    1986.

    B: Gas/Naptha based Thermal Power Plants

    (i) Emission standards for NOx


    (a) For existing units 150 ppm (v/v) at 15% excess oxygen


    (b) For new units with effect from 1-6-1999.

    Generation capacity of gas
    turbine

    Limit for NOx emission (v/v), at 15% excess
    oxygen)

    (a) 400 MW and above

    (i) 50 ppm for the units burning natural gas.
    (ii) 100 ppm for the units burning naphtha

    (b) Less than 400 MW but upto
    100 MW

    (i) 75 ppm for the units burning natural gas
    (ii) 100 ppm for the units burning naphtha

    (c) Less than 100 MW

    100 ppm for units burning natural gas or
    naphtha as fuel

    (d) For the plants burning gas
    in a conventional boiler.

    100 ppm



    (ii) Stack height H in m should be calculated using the formula H= 14 Q 0.3 , where Q is the emission
    of SO2 in kg/hr, subject to a minimum of 30 mts.

    (iii) Liquid waste discharge limit

    Parameter

    Maximum limit of concentration (mg/l except for
    pH and temperature)

    pH

    6.5 - 8.5








    Temperature

    Free available
    chlorine
    Suspended solids
    Oil & grease
    Copper (total)
    Iron (total)
    Zinc
    Chromium (total)
    Phosphate

    As applicable for other thermal power plants

    0.5
    100.0
    20.0
    1.0
    1.0
    1.0
    0.2
    5.0



    C: Liquid fuel based Thermal Power Plants

    (i) Emission Standards for Diesel Engines (Engine Ratingmore Than 0.8 Mw (800 Kw) for Power
    Plant, Generator Set applications and other requirements

    Parameter

    Area
    Category

    Total engine
    rating of the
    plant
    (includes
    existing as
    well as new
    generator
    sets)

    Gerator sets commissioning date

    Before
    1/7/2003

    Between
    1/7/2003 and
    1/7/2005

    On or
    after
    1/7/2005

    Nox (as NO2 ) (at 15% O2 ),
    dry basis, in ppmv

    A

    Upto 75MW

    1100

    970

    710

    B

    Upto 150MW

    A

    More than
    75MW

    1100

    710

    360

    B

    More than
    150MW

    NMHC (as C) (at 15% O2 ),
    mg/Nm3

    Both A and B



    150

    100

    PM (at 15%
    O2 ), mg/Nm3

    Diesel Fuels -
    HSD & LDO

    Both A and B



    75

    75

    Furnace Oils
    - LSHS & FO

    Both A and B



    150

    100

    CO (at 15% O2 ), mg/Nm3

    Both A and B



    150

    150

    Sulphur content in fuel

    A



    <2%

    B



    <4%

    Fuel specification

    For A only

    Up to 5MW

    Only Diesel Fuels (HSD, LDO) shall be
    used.

    Stack height (for generator
    sets commissioned after
    1/7/2003)

    Stack height shall be maximum of the following, in meter:

    I. 14 Q 03 , Q = Total SO2 emission from the plant in kg/hr








    II. inimum 6 m above the building where generator set is installed.

    III. 30 m.



     Note: 1. Acronyms used

    MW : Mega (106 ) Watt, FO : Furnace Oil, NOX : Oxides of Nitrogen HSD : High Speed Diesel, NO2 :
    Nitrogen Dioxide, LDO : Light Diesel Oil, O2 : Oxygen , LSHS : Low Sulphur Heavy Stock, NMHC :
    Non- Methane Hydrocarbon kPa : Kilo Pascal, C : Carbon, mm : Milli (10 -3 ) metre, PM : Particulate
    Matter kg/hr : Kilo (103 ) gram per hour, CO : Carbon Monoxide, mg/Nm3 : Milli (10 -3 ) gram per Normal
    metre cubic, SO2 : Sulphur Dioxide , ppmv : part per million (10 6 ) by volume

    2. Area categories A and B are defined as follows

    Category A: Areas within the municipal limits of towns/cities having population more than 10 lakhs and
    also upto 5 km beyond the municipal limits of such towns/cities.

    Category B: Areas not covered by category A.

    3. The standards shall be regulated by the State Pollution Control Boards or Pollution Control
    Committees, as the case may be.

    4. Individual units with engine ratings less than or equal to 800 KW are not covered by this notification.

     5. Only following liquid fuels viz. High Speed Diesel, Light Diesel Oil, Low Sulphur Heavy Stock and
    Furnace Oil or liquid fuels with equivalent specifications shall be used in these power plants and
    generator sets.

     6. For expansion project, stack height of new generator sets shall be as per total Sulphur Dioxide
    emission (including existing as well as additional load).

    7. For multi engine plants, flues shall be grouped in cluster to get better plume rise and dispersion.
    Provision for any future expansion should be made in planning stage itself.

    8. Particulate Matter, Non-Methane Hydrocarbon and percent moisture (dry basis). Carbon Monoxide
    results -are to be normalized to 25 0 C, 1.01 Kilo Pascal (760 mm of mercury) pressure and zero

     9. Measurement shall be performed at steady load conditions of more than 85% of the rated load.

    10. Continuous monitoring of Oxides of Nitrogen shall be done by the plants whose total engine
    capacity is more than 50 Mega Waft. However, minimum once in six month monitoring for other
    parameters shall be adopted by the plants.

     11. Following methods may be adopted for the measurement of emission parameters,-

    Sl.No.

    Emission Parameters

    Measurement Methods

    1.

    Particulates

    Gravimetric

    2.

    SO2

    Barium Perchlorate- Thorin indicator method

    3.

    NOX

    Chemiluminescence, Non Dispersive Infra Red, Non
    Dispersive Ultra-violet (for continuous measurement),Phenol








    disulphonic method

    4.

    CO

    Non Dispersive Infra Red

    5.

    O2

    Paramagnetic, Electrochemical sensor

    6.

    NMHC

    Gas Chromatograph - Flame lonisation Detector





    LIST OF THERMAL POWER PLANTS IN INDIA

    S. No.

    Name

    State

    Capacity (MW)

    1.

    Ramagundam, NTPC

    Andhra Pradesh

    2100

    2.

    Ramagundam ‘B'

    -do-

    62.5

    3.

    Vijaywada

    -do-

    1260

    4.

    Rayalseema

    -do-

    420

    5

    Simhadri, NTPC

    -do-

    1000

    6.

    Nellore

    -do-

    30

    7.

    Kothagudem

    -do-

    1210

    8.

    Bongaigaon

    Assam

    740

    9.

    Barauni

    Bihar

    320

    10.

    Kahalgoan

    -do-

    840

    11.

    Muzaffarpur

    -do-

    220

    12.

    Korba, NTPC

    Chhattisgarh

    2100

    13.

    Korba East

    -do-

    440

    14.

    Korba [West]

    -do-

    840

    15

    Badarpur,NTPC

    Delhi

    705

    16

    Rajghat

    -do-

    135

    17.

    I.P.Station

    -do-

    247.5

    18.

    Gandhinagar

    Gujrat

    870

    19.

    Utkai

    -do-

    850

    20.

    Wanakbori

    -do-

    1260

    21

    Dhuvaran

    -do-

    534

    22.

    Sabarmati, AEC

    -do-

    400

    23.

    Sikka

    -do-

    240

    24.

    Kutch lignite

    -do-,

    215

    25.

    Surat Lignite

    -do-

    250

    26.

    Faridabad

    Haryana

    180

    27

    Panipat

    -do-

    1150

    28.

    Raichur

    Karnataka

    1470








    29.

    Bokaro ‘B'

    Jharkhand

    630

    30.

    Tenughat

    -do-

    420

    31.

    Patratu

    -do-

    840

    32.

    Bokaro (A)_( Closed0

    -do-



    33.

    Chandrapura

    -do-

    750

    34.

    Amarkantak

    Madhya Pradesh

    290

    35.

    Birsinghpur

    -do-

    840

    36.

    Satpura

    -do-

    1142.5

    37.

    Vindhyachal, NTPC

    -do-

    2760

    38.

    Trombay

    Maharashtra

    1330(500)

    39.

    Khapakheda

    -do-

    840

    40.

    Nasik

    -do-

    910

    41.

    Koradi

    -do-

    1100

    42.

    Bhusawal

    -do-

    482.5

    43.

    Chandrapur

    -do-

    2340

    44.

    Paras

    -do-

    62.5

    45.

    Parli

    -do-

    690

    46.

    Ballarshah (closed)

    -do-



    47.

    Dahanu

    -do-

    500

    48.

    Talcher (N), NTPC

    Orissa

    3000

    49.

    Talcher (old),NTPC

    -do-

    470

    50.

    Ib Valley

    -do-

    420

    51.

    Bhatinda, GNTP

    Punjab

    440

    52.

    GGSSTP,Ropar

    -do-

    1260

    53.

    GHTP (Lehra
    Mohabbat)

    -do-

    420

    54.

    Kota

    Rajasthan

    1045

    55.

    Suratgarh

    -do-

    1250

    56.

    Ennore

    Tamilnadu

    450

    57.

    Tuticorin

    -do-

    1050

    58.

    North Madras

    -do-

    630

    59.

    Mettur

    -do-

    840

    60.

    Neyveli-Lgnite

    -do-

    2490

    61.

    Basin Bridge (Closed)

    -do-



    62.

    Singrauli, NTPC

    Uttar Pradesh

    2000

    63.

    Rihand, NTPC

    -do-

    1000

    64.

    Anpara

    -do-

    1630








    65.

    NCTPS – Dadri,NTPC

    -do-

    840

    66.

    Panki

    -do-

    210

    67.

    Unchahar, NTPC

    -do-

    840

    68.

    Tanda

    -do-

    440

    69.

    Paricha

    -do-

    220

    70.

    Obra A
    Obra B

    -do

    1482

    71.

    Harduaganj

    -do-

    515

    72.

    Farakka,NTPC

    West Bengal

    1600

    73.

    Budge-Budge, CESC

    -do-

    500

    74.

    Mezia, DVC

    -do-

    630

    75.

    Southern, CESC

    -do-

    135

    76.

    Barkeshwar

    -do-

    630

    77.

    Durgapur (DVC)

    -do-

    350

    78.

    Titagarh, CESC

    -do-

    240

    79.

    Santaldih

    -do-

    480

    80.

    DPL, Durgapur

    -do-

    395

    81.

    Kolaghat

    -do-

    1260

    82.

    Bandel

    -do-

    540

    83.

    Gauirpore (closed)

    -do-






    THERMAL POWER PLANTS REQUIRED TO USE BENEFICIATED COAL

    A. EXISTING

    S.
    No.

    Name of Thermal
    Power Station

    Capacity
    (MW)

    Category
    +

    Estimated Annual
    beneficiated Coal
    Requirement (MTPA)

    1.

    Badarpur

    705

    UA

    2.75

    2.

    Indraprastha

    278

    UA

    0.67

    3.

    Rajghat

    135

    UA

    0.58

    4.

    Faridabad

    165

    UA

    0.80*

    5.

    Panipat (Units 1-5)

    650

    >1000 km

    3.60*

    6.

    Bhatinda (Units 1-4)

    440

    >1000 km

    1.98

    7.

    Ropar (Units 1-6)

    1260

    >1000 km

    5.08

    8.

    NCR Dadri

    840

    >1000 km

    4.00

    9.

    Harduaganj

    425

    >1000 km

    1.06

    10.

    Panki

    274

    U.A.

    0.79








    11.

    Paricha

    220

    >1000 km

    0.89

    12.

    Kota (Units 1-5)

    850

    U.A.

    3.65

    13.

    Sabarmati

    410

    U.A.

    1.32*

    14.

    Wanakbori (Units 1-
    6)

    1260

    >1000 km

    6.06

    15.

    Gandhi Nagar

    660

    U.A.

    3.00*

    16.

    Ukai

    850

    >1000 km

    3.36*

    17.

    Sikka (Units 1-2)

    240

    >1000 km

    1.00*

    18.

    Bhusawal

    478

    >1000 km

    2.24

    19.

    Koradi

    1080

    U.A.

    5.50*

    20.

    Nasik

    910

    >1000 km

    3.60

    21.

    Trombay

    1150

    U.A.

    Oil/Coal

    22.

    Dahanu

    500

    S.A.

    2.01

    23.

    DPL

    390

    CPA

    0.49

    24.

    Muddanur
    (Rayalaseema)

    420

    >1000 km

    2.37

    25.

    North Chennai -I

    630

    U.A.

    2.97

    26.

    Ennore

    450

    >1000 km

    1.92*

    27.

    Raichur (1-4)

    840

    >1000 km

    4.38

    28.

    Mettur

    840

    >1000 km

    4.39

    29.

    Tuticorin (1-5)

    1050

    >1000 km

    4.08*

    30.

    Bokaro

    820

    CPA

    1.84

    31.

    Durgapur

    350

    CPA

    1.00

    Sub Total (A)

    19570



    77.37



    B. IX Plan

    S.
    No.

    Name of Thermal
    Power Station

    Capacity
    (MW)

    Category
    +

    Estimated Annual
    Coal Requirement
    (MTPA)

    32.

    Bhatinda-5&6

    420

    >1000 km

    1.88*

    33.

    Wanakbori-7

    210

    >1000 km

    1.00*

    34.

    Gandhinagar-7

    210

    >1000 km

    0.95

    35.

    Raichur (5-6)

    420

    >1000 km

    2.14

    36.

    North Chennai II

    1050

    U.A.

    IC (Imported Coal)

    37.

    Mangalore

    1000

    >1000 km

    IC

    38.

    Tranagallu

    260

    >1000 km

    IC

    39.

    Suratgarh-I

    500

    >1000 km

    IC








    Sub Total (B)

    4370



    8.09



    Total coal consumption based on 1999-2000 data upto ix plan 85.46 mtpa

    * Revised based on data provided by SEBs/utilities

    UA : Urban Area, CPA : Critically Polluted Area, SA: Sensitive Area and

    IC : Imported Coal

    (Source : Central Electricity Authority)

    THERMAL POWER PLANTS WHICH HAVE DRY FLYASH COLLECTION FACILITIES

    1. Dahanu, Maharashtra

    2. Sabarmati, Gujarat

    3. Budge-Budge, West Bengal

    4. Titagarh, West Bengal

    5. Vizaywada, AP

    6. Rayalseema, AP

    7. Kothagundem, AP

    8. Ramagundem ‘B', AP

    9. Nellore , AP

    10. Rajghat, Delhi

    11. Raichur, Karnataka

    12. Singrauli NTPC, UP

    13. Vindhyachal, MP

    14. Ramagundem, AP

    15. *Farakka, West Bengal

    16. *Kahalgaon, Bihar

    17. *Korba, Chhatisgarh

    18. *Talcher (old), Orissa






    19. Talcher (Kaniha N), Orissa

    20. Badarpur, Delhi

    21. Dadri, U.P.

    22. Unchahar, U.P.

    23. DPL, West Bengal

    24. Nasik , Maharashtra

    25. Chandrapur, Maharashtra

    26. Kota , Rajasthan

    27. Ropar, Punjab

    28. Bhatinda, Punjab

    29. Lehra Mohabbat, Punjab

    30. Sabarmati, Gujrat

    31. Suratgarh, Rajasthan

    32. *Neyveli Lignite Corporation,TN

    33. North - Chennai , TN

    34. Ib Valley, Orissa

    35. Meizia ,WB

    36. ** Faridabad , Haryana

    37. **Panipat, Haryana

    38 Sikka, Gujrat

    * : Facility is being provided

    **: PFC has sanctioned the scheme, same is being developed

    Flyash utilization during 2005-06

    State

    Name Capacity

    Capacity

    ( MW)

    Coal
    Cons.

    ( mta)

    Ash Gen.

    ( mta)

    Ash Uti.

    ( mta)

    %

    utilisation






















    Andhra
    Pradesh

    Nellore
    APGENCO

    30

    0.149

    0.065

    0.158

    243

    Andhra
    Pradesh

    Ramagundam ,
    APGENCO

    62.5

    0.283

    0.106

    0.073

    68.9

    Andhra
    Pradesh

    Ramagundam,
    NTPC

    2100

    11.79

    3.887

    1.863

    47.9

    Andhra
    Pradesh

    Rayalseema,
    APGENCO

    420

    1.519

    0.603

    0.386

    61.3

    Andhra
    Pradesh

    Simhadri, NTPC

    1000

    4.98

    1.765

    0.856

    48.5

    Andhra
    Pradesh

    Vijayawada ,
    APGENCO

    1260

    6.81

    2.646

    1.501

    56.7

    Andhra
    Pradesh

    Kothagudem
    APGENCO

    1200

    3.639

    1.507

    Nil

    -















    Assam

    Bongaigaon ,
    ASEB

    710

    Plant
    Closed





















    Bihar

    Barauni

    240

    0.131

    0.052

    0.058

    111.5

    Bihar

    Muzaffarpur,
    BSEB

    220

    Nil

    Nil



    -

    Bihar

    Kahalgaon, NTPC

    840

    5.848

    1.431

    0.703

    49.1















    Chhattisgarh

    Korba, NTPC

    2100

    11.66

    4.832

    2.288

    47.4

    Chhattisgarh

    Korba West

    840

    3.975

    1.75

    0.589

    33.6

    Chhattisgarh

    Korba East,
    ChEB

    440

    2.853

    1.28

    1.155

    90.0















    Delhi

    I.P. .IPPGENCO

    247.5

    0.974

    0.331

    0.157

    47.4

    Delhi

    Rajghat ,
    IPPGENCO

    135

    0.501

    0.172

    0.157

    91.3

    Delhi

    Badarpur, NTPC

    705

    3.77

    0.128

    0.608

    475















    Gujarat

    Ukai, Gujarat
    Elect.Board,

    850

    3.54

    1.157

    0.471

    40.7

    Gujarat

    Gandhi Nagar,
    GEB

    870

    3.17

    0.916

    0.597

    65.2

    Gujarat

    Sikka , GEB

    240

    0.941

    0.278

    0.17

    61.2

    Gujarat

    Sabarmati, AEC,
    Ahmedabad

    400

    1.773

    0.323

    0.304

    94.1








    Gujarat

    Kutchlignite,
    Kutch

    215

    0.735

    0.108

    0.1.08

    100

    Gujarat

    Surat Lignite,

    250

    0.766

    0.303

    0.303

    100

    Gujarat

    Wanakbori

    1470

    6.85

    2.445

    1.546

    63.2















    Haryana

    Panipat

    1360

    3.85

    1.54

    1.668

    108.3

    Haryana

    Faridabd

    165

    0.798

    0.231

    0.029

    12.6















    Jharkhand

    Patratu

    840

    0.812

    0.32

    0.122

    38.1

    Jharkhand

    Chandrapura,
    DVC

    750

    1.396

    0.592

    0.675

    114.0

    Jharkhand

    Bokaro ‘B', DVC

    630

    2.18

    0.715

    0.688

    96.2















    Karnataka

    Raichur, KPCL

    1470

    6.991

    2.269

    0.951

    41.9















    Madhya
    Pradesh

    Satpura MPEB,
    (MP)

    1142.5

    6.936

    2.463

    0.105

    4.3

    Madhya
    Pradesh

    Sanjay Gandhi
    ,MPEB

    840

    4.38

    1.752

    0.589

    33.6

    Madhya
    Pradesh

    Amarkantak ,
    Chachai, MPEB,

    290

    0.977

    0.298

    0.247

    82.9

    Madhya
    Pradesh

    Vindhyachal
    NTPC

    2260

    11

    3.111

    1.463

    47.0















    Maharashtra

    Trombey, Tata
    Poweri

    1330

    1.802

    0.034

    0.0384

    112.9

    Maharashtra

    Koradi, MSEB

    1100

    4.914

    1.744

    0.175

    10.0

    Maharashtra

    Parli , MSEB

    690

    3.799

    1.578

    0.376

    23.8

    Maharashtra

    Bhusawal MSEB

    482.5

    2.394

    0.797

    0.462

    57.9

    Maharashtra

    Dahanu ,
    Relience Energy

    500

    2.37

    0.585

    0.147

    25.1

    Maharashtra

    Khaperkheda,
    MSEB

    840

    4.47

    1.668

    0.634

    38.0

    Maharashtra

    Paras

    62.5

    0.325

    0.102

    0.102

    100

    Maharashtra

    Chandrapur

    2340

    9.557

    3.966

    0.453

    11.4

    Maharashtra

    Nasik

    840

    3.463

    1.247

    0.13

    10.4

    Orissa

    Talcher ,
    Angul,NTPC

    460

    2.82

    1.073

    0.66

    61.5

    Orissa

    Ib. , OPGCL

    420

    2.605

    1.057

    0.07

    6.6






















    Orissa

    Talcher ,
    Kaniha,NTPC

    2500

    13.87

    4.982

    1.232

    24.7















    Punjab

    Gurunanak Dev,
    PSEB

    440

    1.747

    0.539

    0.223

    41.3

    Punjab

    Lehra Mohabat,
    PSEB

    420

    1.83

    0.62

    0.445

    71.8

    Punjab

    GurugobindSingh,
    PSEB

    1260

    6.29

    2.158

    1.626

    75.3

    Rajasthan

    Kota

    1045

    5.325

    1.506

    1.198

    79.5

    Rajasthan

    Suratgrah ,
    RVUNL

    1250

    6.096

    1.759

    0.836

    47.5















    Tamilnadu

    Tuticorin TNEB

    1050

    5.69

    2.116

    0.946

    44.7

    Tamilnadu

    Mettur TNEB

    840

    4.18

    1.514

    1.304

    86.1

    Tamilnadu

    North Chennai ,
    TNEB

    630

    2.54

    0.946

    0.304

    32.1

    Tamilnadu

    Ennore TNEB

    450

    0.58

    0.233

    0.061

    26.2

    Tamilnadu

    NLC, Neyveli

    2490

    15.886

    1.835

    0.499

    27.2

    Tamil nadu

    ST CMS Electric
    (P) Ltd.

    250

    1.442

    0.067

    0.052

    77.6















    Uttar Pardesh

    Unchahar, NTPC

    840

    0.705

    1.838

    1.565

    85.1

    Uttar Pardesh

    Dadari, NTPC

    840

    4.21

    1.507

    0.802

    53.2

    Uttar Pardesh

    Rihand, NTPC

    1000

    4.75

    1.407

    0.73

    51.9

    Uttar Pardesh

    Tanda, NTPC

    440

    2.56

    0.842

    0.402

    47.7

    Uttar Pardesh

    Singrauli, NTPC

    2000

    10.2

    3.123

    1.468

    47.0

    Uttar Pardesh

    Parichha
    ,UPVUNL

    220

    0.726

    0.218

    0.41

    188.1

    Uttar Pardesh

    Obra , UPVUNL

    1550

    4.94

    1.884

    0.014

    0.7

    Uttar Pradesh

    Anpara, UVUNL

    1630

    8.47

    2.974

    0.072

    2.4

    Uttar Pradesh

    Panki, UVUNL

    210

    0.96

    0. 25

    0.337

    133.2















    West Bengal

    Meizia, DVC

    630

    3.32

    1.32

    0.0013

    0.1

    West Bengal

    Durgapur , DVC

    350

    0.872

    0.349

    0.495

    141.8

    West Bengal

    Durgapur Projects
    Ltd.

    401

    1.686

    0.573

    0.737

    128.6

    West Bengal

    Santaldih,
    WBPDCL

    480

    0.843

    0.253

    0.875

    345.8498

    West Bengal

    Budge Budge,

    500

    2.52

    0.908

    0.908

    100








    CESC

    West Bengal

    Titagarh , CESC

    240

    1.17

    0.33

    0.33

    100

    West Bengal

    Sounthern ,
    CESC,

    135

    0.68

    0.24 0.24



    100

    West Bengal

    Kolaghat.
    WBPDCL

    1260

    5.086

    1.618

    1.988

    122.9

    West Bengal

    Farrakka, NTPC

    1600

    9.26

    3.426

    2.06

    60.1

    West Bengal

    Bakreswar,
    WBPDCL

    630

    2.487

    0.689

    0.242

    35.1

    West Bengal

    Bandel, WBPDCL

    530

    1.285

    0.413

    0.18

    43.6

















    Total

    63738.5

    285.742

    95.414

    45.9827

    48.2



    Captive Power plants

    capative
    power
    plants

    Name Capacity

    Capacity

    ( MW)

    Coal Cons.

    ( mta)

    Ash Gen.

    ( mta)

    Ash Uti.

    ( mta)

    %

    utilisation















    UP

    Renusagar,
    HINDALCO

    741.7

    5.43

    2.205

    0.938

    42.5

    Orissa

    NALCO

    55.5

    0.994

    0.414

    0.016

    3.94

    Gujarat

    Tata Chemicals

    70



    0.077

    0.034

    44.2

    Punjab

    NFL, Bhatinda

    *30

    0.122

    0.254



    0

    Karnataka

    Rahshree Cemnet

    38.2



    0.096

    0.305

    317.7

    Kerala

    Hindustan News
    Print

    *22

    0.166

    0.049

    0.049

    100

    AP

    Sirpur Paper Mill

    *31.9

    0.29

    0.139



    0

    Tamilnadu

    TCP Limited

    63.75

    0.373

    0.068

    0.073

    107.4

    AP

    Nava Bharat
    Ferro alloy

    50

    0.276

    0.137

    0.014

    10.2

    Karnataka

    Grasim Industries

    10

    0.089

    0.027

    0.025

    92.6

    Karnataka

    Mysore
    PaperMills

    41

    0.217

    0.05

    0.034

    68

    Gujarat

    JK Paper ltd.

    12

    0.072

    0.028

    0.028

    100

    Orissa

    NTPC-SAIL
    Power Co.

    120

    0.906

    0.362

    0.318

    87.8

    MP

    Orient paper Mills

    22

    0.204

    0.0632

    0.068

    107.6

    Chattisgarh

    Bhilai ESCPL

    74

    0.47

    0.125

    0.0048

    3.84

    UP

    IFFCO

    12.5







    0








    Uttranchal

    CPP-Century
    Pulp & paper

    27.8







    0

    Bihar

    BCCL

    30

    0.164

    0.068

    0.068

    100

    AP

    VSP

    247.5

    1.429

    0.571

    Nil

    0

    Karnataka

    Vasavdatta





    0.047

    0.047

    100

    Orissa

    Nava Bharat
    Ferro alloy

    30

    0.196

    0.095

    0.009

    9.5

    West Bengal

    NTPC-SAIL
    Power Co.

    120

    0.639

    0.25

    0.0562

    22.48

    Jharkhand

    Tata Steel

    147.5

    0.599

    0.281

    Nil

    0

    Maharashtra

    Ballarpur

    30

    0.188

    0.461

    0.0462

    10.0





    1943.45

    12.824

    5.8672

    2.1332

    42.5

    Aug 29, 2010

    BOWL MILLS MAINTANACE -BLUE PRINT

    A Four-Step Plan:

    Blueprinting a pulverizer isn’t rocket science, but it does require close attention to the details. Here is our four-step plan to restore and improve performance of your pulverizer, regardless of its age.
    STEP-I :
    **Ensure that the grinding elements are in good condition.
     Make sure that the grinding surface profiles are optimum. That means using the original design grinding profiles for your mill. The majority of coal pulverizers sized around 120,000 pph use three grinding elements, referred to as journals, rolls, or tires. For best results, all three grinding elements should be replaced in matched sets. The concentricity, physical dimensions, and contours must be exactly the same. This is especially important when maximum preload pressure is required to produce maximum coal fineness and/or with lower-than-original design HGI. We have seen mills assembled with unmatched sets of three grinding journals using maximum spring pressure. The result of such setups: The main shafts break because of the unbalanced load. Matched sets of grinding elements and exactly the same size rolls with exactly the same contour are important for maximum reliability.
    The grinding surfaces also must be in good condition and parallel (Figure 3). Don’t expect optimum performance if the grinding elements are well-worn or the tires are "flat" (Figure 4). Unusual wear patterns are often the result of uneven spring frame tolerances, alignment issues, pressure variations, geometry, and/or eccentricity issues. 



      **Walk the line. The profile of the roll should be parallel with the grinding ring profile.
    ***Perfectly round. In an MPS mill, the tire and table profiles must match, and the tires should not have flat spots.


    .














    STEP-II:
    **Set the correct grinding pressure.  
    Check your mill to confirm that the grinding roll or spring frame preload pressure is set correctly. Our experience with both RP and MPS pulverizers has been that mills designed for a throughput of about 120,000 pounds of coal per hour, an HGI of about 45 to 50, and coal fineness exceeding 75% passing 200 mesh will require about the same force on the grinding elements. It is reasonable to expect that grinding coal will take about the same amount of grinding element pressure regardless of the type of medium-speed, vertical spindle pulverizers you use.
    In our experience the spring frame of an MPS mill tuned for maximum true capacity will be set at about 20 tons minimum force on the grinding tires. A bowl mill spring or hydraulic preload for this size of mill will also be about 20 tons of pressure. Lower-HGI fuel and greater than passing of 200 mesh requires the maximum pressure of the grinding elements. Keep in mind that in operation there is no metal-to-metal contact, and all coal grinding results from the pressure applied coal particle – to – coal particle on a bed of coal squeezed between the grinding elements.
    Internal clearances are also very important. For example, a bowl mill spring canister can be set to the needed preload, but if it is not adjusted for the "button" to roll with assembly minimum clearance, then the preloading does not come into play until the roll rides up on a deeper bed of coal . Ensuring sufficient grinding pressure is absolutely essential, and it begins with setting this critical tolerance.


    ** Keep your distance. The "button" clearance between the spring canister and the journal assembly is a critical tolerance.
    For a spring frame mill, the hydraulic preload must be balanced across the mill and the grinding elements perfectly centered in the assembly

    * *Balanced load. The MPS spring frame hydraulic preload must be carefully balanced and the spring frame centered for optimum mill performance. 

    STEP-III:
    ** Set the correct pulverizer throat clearance. An oversized pulverizer throat will require more than optimum primary airflow to minimize coal rejects. The pulverizer "free annular jet" of vertically flowing airflow, in our experience, must be adjusted for a minimum of 7,000 fpm under normal operation. Throats that are oversized will result in either excessive coal rejects (not tramp metal or pyrites, but raw coal).
    Compounding the problem, high primary airflow is the main cause, in our experience, for poor fuel fineness, poor fuel distribution, and reduced furnace performance. Right-sizing the flow area of the pulverizer throats and matching them for compatibility with the coal pipes and burner nozzle sizes is essential for the best furnace performance. Furthermore, remember that there will be minor variation in mill capacity, fuel quality, and mill inlet airflow rates that must be considered when sizing the pulverizer throat flow area.
    The vertically flowing air must be of sufficient velocity to suspend the granular coal bed in the grinding zone. Some designs use mechanical means to keep the coal above the under-bowl pyrite section, while others use airflow. Reducing coal rejects by mechanical means entails increasing the height of the "bull ring" extension ring or the extension of flat surfaces above the rotating throat to trap or dam coal particles mechanically so that they remain above the throat.
    We prefer the optimum throat area fluidic solution to suspend the coal bed and reduce the potential for fires beneath the bowl or grinding table. Keep in mind that if the fuel is above 17% moisture and the air/fuel ratio is about 1.8, then the under-bowl primary air temperature will be above 450F. Any coal that falls through the throat opening will combust unless it is removed in mere minutes. Combustion of coal particles beneath the grinding zone is not a serious problem, as long as the mill is in operation. But if a mill trips or a boiler has a main fuel trip, then fires in the pyrites zone (beneath the grinding zone) are the most common cause of pulverizer "puffs," in our experience. A fire beneath the grinding zone provides the ignition temperature to initiate a mill "puff" when restarting a mill after a trip or restarting it after a main fuel trip when coal remains in the bed.
    For safety as well as for performance reasons, properly sizing the mill throats is extremely important . The optimum throat area is determined by calculating the free annular jet area when the desired air/fuel ratio (usually 1.8 lb air/lb fuel) is known. Also, the throat area must be properly designed to be compatible with the flow areas of the burner coal pipes and coal nozzles

    **Optimum design. Ensure optimum arrangement of the mill throat and the coal flow path to improve mill performance.

    **Close tolerances. Pulverized coal mills with throats that are too wide will have corresponding low throat velocity in the mill grinding zone that contributes to excessive coal rejects and fires. This is an example of an oversized mill throat.
    STEP-IV:
    **Properly maintain the classifier.
    Once the grinding zone is blueprinted and put in first-class condition, the next component to examine is the classifier. The best furnace combustion performance is governed by uniform coal combustion by the burners and satisfactory coal fineness. Adequate fineness for both western and eastern fuels (Powder River Basin or bituminous) is a minimum of 75% to 80% passing 200 mesh and zero to 0.1% remaining on a 50 mesh screen (Figure 9). To achieve this fineness, the pressurized mill classifier must perform two functions:
    ·   **      It separates particles small enough to be supplied to the burners (mean particle size about 40 to 55 microns) from larger coal particles that need return to the grinding zone for regrinding.
    ·     **    It balances the distribution of coal to each coal pipe.



    **Why use a classifier? A classifier recirculates coarse coal in the grinding zone and balances the flow of coal to each burner line to the furnace.
    The flow of coal particles through a classifier is several times the amount of coal flowing to the burners because of the large amount of coal recirculated within a pulverizer. For example, if a pulverizer is operating at 100,000 lb/hr coal feed to the burners, as much as 300,000 lb/hr or more may be flowing through the classifier for regrinding. For this reason the surface smoothness and inverted cone clearances are extremely important for good pulverizer performance.
    Our experience over the years has helped us develop a number of proven minor enhancements for achieving best classifier performance. The critical dimensions indicated in Figure 10 include:
    ·         Surface smoothness of the classifier cone.
    ·         Synchronized classifier blade angles and lengths.
    ·         Inverted cone to classifier clearances.
    ·         Classifier outlet cylinder length and flared opening.
    ·         
    **Better than good. Areas of the classifier where performance can be improved.

    Other improvements that should be considered when overhauling a classifier include these:
    ·         Smooth surfaces in the upper turret section for good fuel spinning and uniform distribution (no surface discontinuities, such as "pad eyes").
    ·         Ensure the free movement and closure of the discharge doors (trickle valves).
    ·         Confirm the sound and good condition of the classifier cone assembly (no holes should be worn through).
    ·         Ensure the good mechanical condition of the classifier blades.

    ** Mill design guide. An internal view of  a typical vertical-spindle pulverizer and specific areas where special attention to dimensional tolerances and assembly dimensions can improve mill performance.